HomeTop StoriesMajor milestone for Gap’s reconstruction

Major milestone for Gap’s reconstruction

Hundreds of 10-metre soil nails have been driven beneath the road near the top of Cunningham’s Gap as part of the $40 million reconstruction program under Operation Queenslander.
About 450 soil nails out of a total of 700 have been used to stabilise a 100 metre long section of the east-bound lane up to six metres deep under the road, at a site 15 metres from the top of the Gap, to provide a solid and safe road base.
Main Roads Minister Craig Wallace said a chunk of the range had been excavated to give the crews installing the nails access under the road.
“This continues to be a mammoth task but it’s all about using these huge soil nails to reinforce the road foundation, creating a permanent and stable road for the many motorists who rely on this vital link,” Mr Wallace said.
“Once the remaining 250 soil nails have been driven even deeper into the rock face beneath this section, we can rebuild the excavated site with rock fill and then rebuild the road.”
Mr Wallace said the work at Cunningham’s Gap was being delivered under the Natural Disaster Relief and Recovery Arrangements (NDRRA), a joint federal and state initiative.
“Under NDRRA, the Gillard Government provides 75 per cent of the funding, with 25 per cent from the Bligh Government,” he said.
Mr Wallace said the work crew had completed this stage of works in record time, while causing as little disruption to road users as possible.
“When we’re finished here, the road will be safer than it’s ever been before,” he said.
“With 80 workers on site at the Gap, our contractor is committed to supporting local businesses – from the motels where workers are staying, to nearby service stations, trade suppliers and even the local pie shop.
“Seven local jobs have been made available through the project, with further opportunities expected in the future.”
There are 11 locations along a seven-kilometre-stretch of the highway requiring extensive work to repair damage from landslips and road subsidence from heavy rain. Four are underway, two are complete and two are set to start shortly. The remaining three sites are in detailed design and set to start within the next few months.
“Crews are working around the clock to deliver these essential works as quickly as possible. However, safety is the department’s number one priority,” Mr Wallace said.
Restrictions are in place between the helipad and the top of the Gap on vehicles over 3.5 metres wide and/or over 26 metres long (excluding B-doubles) to allow the reconstruction work along the route to be carried out. Oversize vehicles are encouraged to take alternate routes.
Motorists can subscribe for SMS updates on the traffic conditions at the Gap by visiting www.cunninghamhighwaysms.com.au. For the latest road conditions and closures in your area, visit www.131940.qld.gov.au or call 131 940.

Digital Edition
Subscribe

Get an all ACCESS PASS to the News and your Digital Edition with an online subscription

Fears region headed for drought as dry spell bites

Increasingly dry conditions and bleak long-term rainfall outlooks have forced farmers into offloading livestock and rethinking this year’s cropping season amid fears the region...
More News

Hard-fought win for Wattles

Wattles Warriors had to fight hard to open their 2026 Toowoomba Rugby League premiership campaign with a 32 – 26 victory over the Highfields...

Cowboys come out firing

The Warwick Cowboys showed they mean business opening their 40th Toowoomba Rugby League season with three impressive wins across the grades against Souths on...

The bravest of the brave

The Shrine of Remembrance in Warwick’s Leslie Park contains many names of enlisted men and women who answered the call in 1915 to help...

Midwifery boost for regional healthcare as new program rolls out

A new state-wide Midwife program coming to the Darling Downs could see an increased midwife-to-patient ratio in an effort to make health care more...

Cold morning blast sweeps across Southern Downs

An early taste of winter greeted Southern Downs residents on Monday morning with temperatures plunging to below zero degrees in parts of the region. The...

Telstra upgrade to disrupt Karara mobile service

Telstra mobile phone customers in Karara can expect temporary disruptions this month while the telco upgrades its base station. The works are scheduled to begin...

Evans wins exciting stableford

An exciting Warwick Women’s Single Stableford on Wednesday 9 April had to be decided on a countback after three golfers tied for first. Di...

End of an era

Stanthorpe Croquet Members gathered on Wednesday, 8 April to farewell Joy Newman who has decided to retire from the game she loves after 34. Joy...

Markets feel the heat of weather and rising costs

Numbers were mixed this week as we settle into the normality of the 5-day week after the Easter break. Cattle saw a yarding of...

Good roll-up for Easter Saturday bowls

Players from around South East Queensland took advantage of good Easter holiday conditions to for a game of social bowls at The Summit –...