ONCE the CRG recommendation has been finalised on a power line route/corridor, the recommendation will still need to be tested for its suitability and constructability when the decision becomes firm. Ergon’s internal processes are for the CRG recommendations to be reviewed by the Network Investment Review Committee (NIRC). The recommendation is then taken to the Ergon board that will make the final decision. Ergon will then be seeking sign-off from the Energy Minister through the Ministerial Designation process. This process also incorporates additional community engagement.